The gymnasium will be closed for resurfacing Monday, August 6, through Sunday, September 2, re-opening on Monday, September 3, 2018.
Click HERE for a detailed gymnasium schedule. Thank you for your patience while we improve The Lodge!
Monday, 8/20 - layer of sealer is applied (strong smell day)
Tuesday, 8/21 - buff sealer and begin process for game lines
Wednesday, 8/22 - paint game lines
Friday, 8/24 - put down first layer of final seal (strong smell day)
Monday, 8/27 - put down final layer of final seal (strong smell day)
Monday, 9/3 - the gymnasium will re-open to members/guests