Oak Drive Bridge Replacement

Project Summary
The Oak Drive Bridge over Two-Mile Creek is scheduled for replacement in 2018.  The City obtained a federal grant, by which 80% of the costs will be reimbursed. 

Project Update and Schedule

The City received final approval from MoDOT on 1/12/18, and intends to advertise for bids by 1/19/18.  A link to the full plans and specs will be available at that time.  Work is tentatively scheduled to start after Memorial Day.

Last updated 1/12/18